Investment Hotline : 86-769-22817370
Website : Invest In China
E-mail : fipc@dg.gov.cn

Environment Protection Administration

I. Approval

Assess the probability to pollute environment imposed by the project

II. Documents Required by Approval

A. Environment Impact Report

B. Environment Impact Report Sheet

C. Environment Impact Registration Sheet

III. Instructions about document preparation for approval

A. As per Environmental Protection of Construction Project Regulations (State Congress Ordinance No.253), it is mandated to assess the environment impact for all construction projects that could impose pollution upon environment. Environment Impact Report should be prepared by qualified authorities listed as follows (included but not limited to):

Dongguan Environment Science Institute Telephone: 0769-2477542

South China Environment Science Institute, National Environment Protection General Administration Telephone: 020-85538229

Environment Science Institute of Zhongshan University Telephone: 020-84112293

Guangzhou Environment Protection Science Institute Telephone: 020-87592191

Environment & Resources Engineering Department of Guangdong Industry University Telephone: 020-87766069-6540

Environment Impact Assessment Office, Environment Protection School of Guangdong Telephone: 020-85520337

B. Investors can select one from above-mentioned options or other equivalent environment assessment authorities to prepare the Environment Impact Report(sheet).

C. Documents required to be submitted by the environment assessment authorities

1. Brief Introduction of Construction Project: total project investment, location, ambient environment, occupancy in area, factory layout and headcount etc.

2. Basic Information about the Production: product, annual output, main raw material and amount (annual consumption) and production techniques etc.

3. Pollution Status & Treatment Measures: production pollution procedures, pollutant (waste water, waste gas and waste sludge) discharge amount and concentration, disposal of pollutant and environment pollution preventive measures etc.

Documents presented above are commonly required to be submitted. As for different construction projects, the specific request about documents claimed by the environment impact assessment authorities should prevail.

D. When the Environment Impact Report (sheet) is ready, please go to the local branch of the Environment Protection Administration with the report for preliminary approval.

E. Regarding project discharging excessive pollutants including waste water, waste gas and noise as well, together with the Environment Impact Report (sheet) the Environment Pollution Treatment Facility Design Proposal should be submitted.

F. The Environment Pollution Treatment Facility Design Proposal shall be stipulated by the qualified environment engineering design institute (the environment engineering design institute situated outside Dongguan should register in the Environment Protection Administration of Dongguan). At present, there are 40 qualified environment engineering design institutes inside and outside Dongguan in total. If required, make contact with the Environment Protection Administration of Dongguan or branches situated in different towns or counties.

IV. Procedures

A. Fill out the Environment Protection Application Form for Construction Project of Guangdong and branches of the Environment Protection Administration of Dongguan situated in different towns or counties are responsible for formulating the Environment Impact Report (sheet) as well as registration table. And the final result is due out within 3 workdays.

B. As for projects that could bring forth serious impact upon environment, it is mandated to formulate the Environment Impact Report by qualified assessment organizations appointed by investors at their own discretion. As soon as making comments about the report by the branches of the Environment Protection Administration of Dongguan situated in different towns or counties, the Environment Impact Report should be sent to the Environment Protection Administration of Dongguan for approval. And the Environment Impact Report should be approved within 25 workdays.

C. As for projects that could bring forth slight impact upon environment, it is mandated to formulate the Environment Impact Report by qualified assessment organizations appointed by investors at their own discretion. As soon as making comments about the report by the branches of the Environment Protection Administration of Dongguan situated in different towns or counties, the Environment Impact Report should be sent to the Environment Protection Administration of Dongguan for approval. And the Environment Impact Report should be approved within 12 workdays.

D. As for projects that could bring forth trivial impact upon environment, it is mandated to formulate the Environment Impact Registration Sheet by investors at their own discretion. As soon as making comments about the registration sheet by the branches of the Environment Protection Administration of Dongguan situated in different towns or counties within 5 workdays, the Environment Registration Sheet should be sent to the Environment Protection Administration of Dongguan for filing.

Welcome

Dongguan is a newly-rising industrialized city in China, which is well-known for its developed manufacturing and industrial chain. Meanwhile, it is an international manufacturing base with pillar industries of electronic information, communication equipment, textile and garment, furniture, building material, toy, paper-making, food and beverage, hardware and plastics, etc. Take Dongguan’s IT industry for example, more than 3700 enterprises establish an important manufacturing base and sourcing center of IT products in the world.

What's New

Mayor of Dongguan city, Yuan Baocheng, met the Hungarian delegation led by Istvan Uihelyi, vice chairman of Hungary Parliament, on November 18th.
China Foreign Trade E-Commerce Meet ing & The 2nd FTF Annual Meeting 2012 was held in Song Shan Lake, central part of Dongguan city, on November 8th.
China Processing Trade Products Fair (CPTPF), held from September 16 to 19, consisted of 10 special events such as the high-level forum for development of processing trade, high-level dialog of circulation trade enterprises and processing trade enterprises and procurement linkage, which increased the influence and effectiveness of CPTPF and achieved a win-win deal.
Humen Port succeeded in attracting the project of South China Petrochemical Trading Center, up to 3 billion RMB, at a recent promotion in Shenzhen.

SITELINK: